Sign in to continue:

Monday, July 27th, 2026

U.S. Gold Corp. Announces Robust Feasibility Study for CK Gold Project With $632M NPV, 27% IRR, and Full Permits in Wyoming





U.S. Gold Corp. Releases Robust Feasibility Study for CK Gold Project – Major Milestone with Price-Moving Details

U.S. Gold Corp. Delivers Strong Feasibility Study for CK Gold Project, Wyoming: All Permits in Hand, Exceptional Economics, and Pathway to Expansion

Summary

  • U.S. Gold Corp. (NASDAQ: USAU) has announced the results of its Feasibility Study (FS) for the wholly owned CK Gold Project in southeast Wyoming, a project now fully permitted and ready for construction.
  • Project highlights include: 11-year mine life, strong project returns, low initial capital, rapid payback, robust free cash flow, and significant expansion potential.
  • All permits required for construction are in hand, de-risking the development timeline and positioning the company to capitalize on the current high gold, copper, and silver price environment.

Key Feasibility Study Highlights

  • Robust Project Economics:
    • After-tax NPV (5%) of \$632 million and IRR of 27% at base case prices (\$3,250/oz gold, \$4.50/lb copper, \$40/oz silver).
    • At recent spot prices (\$4,500/oz gold, \$5.50/lb copper, \$70/oz silver): After-tax NPV (5%) increases to \$1.30 billion and IRR to 45%.
    • NPV-to-capex ratio of 1.6 (base case), improving to 3.3 at spot prices. Payback period as low as 1.6 years at spot.
  • Low Risk, Fully Permitted Development:
    • All necessary permits for construction and operation secured. \$5 million reclamation bond in place to cover first year construction.
    • Located just 20 miles from Cheyenne, WY, with excellent access to infrastructure, workforce, services, and logistics.
    • Jurisdictional stability with strong local and state support.
  • Production and Cost Profile:
    • 11-year mine life with a focus on early high-grade extraction. Average sales of 102,000 oz AuEq (gold equivalent) per year from years 2-8; LOM average 85,000 oz AuEq/year.
    • Low strip ratio of 0.89:1 and minimal pre-stripping, enhancing economics and reducing mining risk.
    • Life-of-mine (LOM) total cash costs (co-product basis) of \$1,748/oz AuEq and all-in sustaining cost (AISC) of \$1,814/oz AuEq.
    • Initial capital cost (including contingency): \$394 million. Sustaining capital: \$35 million over LOM. Additional owner’s costs and closure: \$28 million and \$27 million, respectively.
  • Strong Free Cash Flow:
    • Year 2–8 average annual after-tax free cash flow of \$160 million, with a total LOM free cash flow of \$967 million (including capital investment and closure).
  • Simple Processing & Compact Layout:
    • ~80-acre open pit. Ore processed via SAG-ball mill-flotation circuit, producing a clean gold-rich copper concentrate.
    • Dry-stack tailings for efficient water use and environmental management.
  • Significant Community and Stakeholder Benefits:
    • 2.1% royalty payments earmarked for K-12 education in Wyoming.
    • Creation of ~198 direct permanent jobs. Strong community support, no significant cultural or archaeological impacts.
  • Expansion and Aggregate Revenue Upside:
    • Significant measured and indicated resources excluded from initial mine plan to avoid a dry drainage, but remain available for future expansion pending further permitting and drilling.
    • Potential for additional aggregate sales (from high-quality waste rock) into the Rocky Mountain region, not included in the FS economic model.
    • Possibility of converting the final pit to a recreational or water reservoir post-mining, potentially reducing reclamation costs.
  • Excellent Timing and Market Conditions:
    • CK is one of very few fully permitted, large-scale precious metal projects at FS stage in the U.S., with strong gold-copper-silver prices and supportive U.S. policy on domestic mineral security.

Detailed Project and Financial Metrics

Mining & Reserves

  • Total ore mined: 74.5 million short tons (Mst), containing 1.015 Moz gold, 260 Mlb copper, 3.03 Moz silver.
  • Proven and Probable Reserves: 1.015 Moz gold, 260 Mlb copper, 1.6 Moz AuEq.
  • LOM average grades: 0.014 oz/t Au, 0.174% Cu, 0.041 oz/t Ag.

Metallurgical Recovery

  • LOM average recoveries: 71.5% gold, 80.6% copper, 68.7% silver.
  • Payable metals: 707 koz gold, 186.7 Mlb copper, 1.87 Moz silver.

Operating & Capital Costs

  • Mining cost: \$3.88/t mined; \$7.33/t processed.
  • Processing cost: \$9.59/t processed; G&A: \$1.54/t processed.
  • Total site operating cost: \$18.46/t processed.
  • Initial capital: \$394 million; sustaining capital: \$35 million; pre-production owner’s cost: \$28 million; reclamation: \$27 million; total LOM capital: \$483.9 million.

Project Sensitivities

  • Every \$250/oz change in gold price has a significant impact on NPV and IRR: At \$4,000/oz gold, after-tax NPV (5%) is \$946M, IRR 36.3%, payback 1.8 years. At \$5,000/oz gold, NPV (5%) is \$1.36B, IRR 47.4%, payback 1.4 years.
  • At \$1,500/oz gold, project is not viable, highlighting the importance of prevailing metal prices.

Permitting, Environment, and Community

  • All major permits for construction and operation have been obtained. The project employs dry-stack tailings to minimize water use and environmental risk.
  • Local engagement has been substantial, with no significant cultural or environmental findings that could delay or impact the project.
  • ESG: Achieved an “A” rating on Digbee Ltd. (independent ESG disclosure platform) assessment.

Infrastructure Advantages

  • Close to Cheyenne (Wyoming’s state capital), with ready access to workforce, suppliers, and services. No need for man-camp or extensive onsite offices.
  • 30 MW power supply secured via Black Hills Energy, backup generator planned.
  • Water supplied under contract from Cheyenne Board of Public Utilities.
  • Onsite facilities limited to essentials, with offsite support available in Cheyenne.

Exploration and Expansion Potential

  • Significant additional measured, indicated, and inferred resources outside the current reserve pit shell. Expansion drilling and permitting could extend mine life and increase project value.
  • Aggregate and rail ballast sales not included in the feasibility study, representing further upside.

Next Steps and Timeline

  • Project financing is the immediate next step, with all permits in hand.
  • Detailed engineering will commence post-financing; early civil works (access road, aggregate quarrying) are already underway.
  • No formal production decision yet; will follow detailed engineering, Board approval, and financing arrangements.
  • US Gold will host a webcast to discuss the FS and take Q&A from investors and analysts.

What Shareholders Need to Know (Potentially Price-Sensitive Information)

  • The CK Gold Project is fully permitted and de-risked for construction – an extremely rare situation for a large-scale U.S. gold-copper project.
  • The project generates robust economics at current and higher metal prices, with significant leverage to any further increases in gold, copper, or silver prices.
  • Potential for rapid payback (as low as 1.6 years at spot prices), strong free cash flow, and a clear path to expansion and additional revenue streams (including aggregate sales).
  • Strong local and state support, ESG credentials, and minimal environmental/cultural risks further reduce development risk and enhance project attractiveness to financiers, strategic partners, and potential acquirers.
  • Any progress on project financing, a production decision, or partnership announcements could be major share price catalysts.

Conclusion

The CK Gold Project’s feasibility study is a major milestone for U.S. Gold Corp., transforming the company into a near-term U.S. gold-copper producer with a low-risk, high-return project. With all permits in hand, robust economics, and significant expansion and upside potential, shareholders have multiple value-creation catalysts ahead. Investors should closely monitor developments on project financing, construction start, and resource expansion, as these could materially move the share price.


Disclaimer: This article is for informational purposes only and does not constitute investment advice. The information is based on publicly available documents and may contain forward-looking statements subject to risks and uncertainties. Investors should conduct their own due diligence and consult with their financial advisors before making investment decisions. Please refer to U.S. Gold Corp.’s filings with the U.S. Securities and Exchange Commission for further details and risk disclosures.




View U.S. GOLD CORP. Historical chart here



Ryan Specialty Holdings Increases Share Repurchase Program by $300 Million

Ryan Specialty Holdings Announces Major \$300 Million Increa...

Wellgistics Health, Inc. 2025 Annual Report: Leadership, Compliance, and Key Corporate Governance Disclosures

Wellgistics Health, Inc. 10-K/A Amendment No. 1: Key Investo...